How Long Does a Bathroom Renovation Take?

December 20, 2023

There is something exciting about a bathroom remodel project, knowing that you are going to end up with a fresh, rejuvenated and modern room in your home.

However, though you might have a vision of what you would like your bathroom renovation to look like, you also need to think about the time that the project will take to complete.

From the initial demolition of an existing bathroom to the finishing touches, it’s important to have a good idea of how long it will take to turn your bathroom dreams into a reality.

Whether you are planning a modest refresh of an existing bathroom or a complete overhaul, the information below will guide you through the bathroom renovation timeline.

The Average Time Taken for Bathroom Renovations

It’s difficult to give an exact figure for how long a bathroom renovation takes, as there are a variety of things to take into account but you should plan for at least three to four weeks of work, if not more.

A modern bathroom with blue tiles

Whereas a small and simple bathroom remodel can be a relatively quick home improvement project, a complete bathroom renovation and creating a bathroom from scratch can take a lot longer.

This is why it’s important to make sure that you have enough time for your chosen tradespeople to complete the job, especially if you are having a full bathroom renovation.

Remodelling

The time taken for bathroom remodels can vary, and remodelling an existing bathroom is usually slightly quicker. Remodelling an existing bathroom involves updating fixtures, finishes, and possibly reconfiguring the layout, but it doesn’t involve creating a bathroom from scratch.

On average, you should anticipate a timeline of between three to four weeks for this type of project.

The process typically includes demolishing existing bathroom elements, addressing plumbing and electrical work, installing new fixtures and completing the finishing touches. Of course, timelines can vary based on the scope of the project and the complexity of the changes.

If the remodelling is more complex or if the bathroom is especially large, the timeline could be longer.

New Bathroom

Constructing a completely new bathroom from scratch, where there wasn’t a bathroom before, naturally demands more time and intricate planning than a simple remodel.

On average, you can expect a timeframe of anywhere from three to four weeks, to eight to nine weeks for the complete bathroom installation. The time it takes to renovate a new bathroom depends on a lot of factors, with large and more complex projects taking a lot longer than small, simple renovations.

This timeframe includes the entire process, from the initial bathroom design and layout considerations to the installation of plumbing, electrical work and adding the final fixtures. The duration of a new bathroom renovation is determined by the scale of the project, any bespoke design elements and any unforeseen challenges, which often result in delays.

Time to Plan

There is a lot that goes into planning a bathroom renovation, and it’s not something that you quickly jump into. A lot of people underestimate the importance of planning a bathroom renovation, but it’s the planning stages that result in a straightforward renovation or remodel, resulting in a bathroom that ticks every box.

It can take anywhere from a few weeks to a few months to plan a bathroom renovation, as the following stages need to be completed before demolition can begin.

Inspiration

The first part of planning a bathroom renovation is finding inspiration and deciding on your vision. You need to have adequate time to look at various design trends, think about your desired aesthetic and consider the functional aspects of your bathroom.

Budgeting

Once your vision is solidified, you can then start thinking about budgeting. This stage of planning involves assessing costs, obtaining quotes from tradespeople and ensuring that your budget aligns with your renovation goals.

Layout and Fixtures

Designing the layout of your new bathroom and selecting fixtures is a key part of the planning process, and it’s a stage that demands careful consideration. This stage tends to involve consulting designers, finalising floor plans, choosing fixtures and ensuring the design aligns with your preferences and budget.

Contractor Selection

Finding the right contractor is a vital part of a successful bathroom renovation. You need to allocate enough time to researching and selecting a reputable professional, checking references and finalising contractual agreements.

Material Selection

Choosing materials – such as wall tiles, counters and fixtures – can take a few days, or it could take a few weeks, depending on how easy it is to find the materials that you are looking for. Consider factors like availability, delivery times and any customisation requirements before making your final decision.

Bathroom Renovation Timeline

A bathroom sink with white tiles around it

Starting a bathroom renovation project can be daunting, even if it’s part of the journey towards transforming a functional space into your dream bathroom. Understanding the flow of tasks is essential for a smooth renovation process, and it reduces the chances of you being caught out by a renovation going on for longer than you planned.

Old Bathroom Removal

Before a bathroom renovation can begin, the old or existing bathroom needs to be removed. This typically takes one to two days, involves the dismantling of fixtures, tiles and any existing structures. The time it takes to remove the old bathroom depends on a lot of things, such as the amount of material to remove, and how difficult the material is to demolish.

Plumbing

Once the space is cleared, plumbing work can commence. This stage, usually lasting two to three days, involves any necessary reconfigurations, installations or repairs to ensure optimal functionality. If you are having a building created from scratch, more extensive plumbing could be required, and this will require more time.

Installing Bathroom Suite

The installation of the new bathroom suite follows plumbing. This stage spans two to four days, depending on how large or complex the suite is. This construction phase incorporates setting fixtures such as sinks, toilets, shower cubicle and baths, ensuring they align with the planned layout.

Electrical

Electrical work is conducted after the bathroom suite installation. This stage takes approximately one to two days, including wiring for lighting, outlets and any other electrical components.

Sheeting

Sheeting involves preparing the walls for the upcoming finishes. You should allocate one to two days for this stage, ensuring a smooth and even surface for the rest of the renovation. For larger rooms, this could take slightly longer.

Waterproofing

Waterproofing is a critical step to protect your bathroom from potential water damage. This phase typically takes two to three days, as a perfect application is key.

Tiling

Tiling is a transformative stage that adds aesthetic appeal to a bathroom. You should plan for tiling to take approximately three to five days, but it can take longer depending on the size of the space and complexity of the chosen tile pattern.

Painting

Once tiling is complete, painting the walls and ceilings is next. This stage requires one to two days to ensure a flawless finish that complements the overall design.

Fittings

Fittings such as mirrors, shelves and towel racks are added in the final stages. You should allocate one to two days for fitting these accessories, depending on how much you are adding to the room. Once the fittings have been added, you will notice an immediate improvement to how functional the space looks, whilst also improving the way the room looks.

Finding Someone to Renovate Your Bathroom

A plumber fixing under the sink

There is a lot of excitement surrounding a bathroom renovation, but finding the right professional to bring your vision to life is an important first step. There are a variety of ways to find someone to renovate your bathroom including searching online, asking around and using The Page.

The Page

With The Page, finding a bathroom fitter is easier than it ever has been.

When looking for a tradesman, such as someone to renovate your bathroom, you can submit an inquiry to The Page, and wait to be matched with a curated list of professionals tailored to your specific job requirements. The Page is committed to ensuring quality and reliability, for both customers and tradespeople.

Every tradesman featured on the platform undergoes a vetting process, involving face-to-face meetings and comprehensive assessments of their previous work.

This dedication to evaluating tradespeople guarantees that users are connected with only the most qualified and reputable tradesmen in the area, providing peace of mind and confidence for any bathroom renovation project.

Send us an enquiry and we will create a tailored list of suitable tradesmen for you.

Online Search

Technology has revolutionised the way we look for service providers and tradespeople online, making online searches a ‘go-to’ method for finding a bathroom renovation professional.

You can use search engines, such as Google, to find local bathroom renovation specialists. You can also use platforms like Trustpilot, Yelp and The Page, all of which provide a range of reviewed and recommended tradespeople for you to choose from.

Assessing the experiences of previous clients can offer valuable insights into a professional’s reliability and work quality, so check out online reviews and testimonials.

Ask Around

It’s always a good idea to ask around when it comes to finding someone to complete your bathroom refurbishment. Personal recommendations carry a lot of weight, and asking around can give you an insight into who other people have previously used.

Seek recommendations from friends, family or neighbours who have recently undertaken bathroom renovations. Personal referrals often come with detailed information about the professional’s quality of work, communication and overall performance.

You could also ask within local community groups or forums, either online or offline. Neighbours who have undergone renovations can share their experiences and recommend professionals they trust, many of which are likely to be local to you.

While the timelines provided offer a general roadmap, it’s important to embrace flexibility and recognise that unexpected challenges and bespoke design choices can influence the overall duration.

Whether you are envisioning a quick refresh or a more extensive overhaul, the key lies in informed planning, collaboration with skilled professionals and an understanding that high-quality, impressive and worthwhile renovations require an investment of time.

Free Tradesperson Shortlist

Let The Page curate you a bespoke shortlist of tradespeople suited to you and your job.

Contact us

Our Promise

We started The Page because we both had terrible experiences with tradespeople in London and were adamant we would help others to avoid this.

We also know that things can go wrong sometimes, so our promise is to be here to sort things out when they do.

As a result, along with our strong relationships with all our tradespeople, we have our good deed piggy bank, which we give out at our discretion if something goes wrong.